Speirs Wharf Office Fit Out

 

Project Team

Client: Safehinge Primera

Location: Glasgow

Office Fit Out: Elmwood Projects

 

 Speirs Wharf

The delivery of this office fit out, just north of the M8 motorway as it cuts through Glasgow city centre, involved the management, coordination and delivery of;

 

•Waterproofing
•Electrical 1st & 2nd Fix
•Mechanical 1st & 2nd Fix
•Plumbing 1st & 2nd Fix
•Joinery 1st & 2nd Fix
•Floor Coverings
•Taping & Filling
•Installation of glazed partitions
•Installation of Staircase & Balustrade
•Installation of Safehinge Primera doors
•Installation of Manufactured Items
•Toilet Vanity Units
•Installation of Kitchen to the Mezzanine
•Tiling, Service of roller shutters
•Decoration

The site proved challenging in terms of access given the extremely narrow and restrictive drive in route to the wharf, as well as parking and subsequent communal building stairwell access to the office. The co-ordination of all trades was essential from the outset to ensure sufficient installations of all the above trades to the main floor (1st floor of building) and mezzanine areas.

 

Utilising our experience and robust procedures, we were able to deliver the full refurbishment of the previously stripped out offices, to form new meeting room, kitchen at mezzanine level, formation of stairs between the levels full services replacement, floor coverings, decoration, damp proofing and under floor heating – with the end result being a fresh, vibrant, light and contemporary finish, that’s suitable for a modern day workforce to thrive in comfort and productivity in such a sought after office location.